Bond 2022 update: high school 37% complete, Fulton Elementary 81% complete

Rockport-Fulton Independent School District Board of Trustees · January 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Claycomb Associates and Teal Construction told the Rockport‑Fulton ISD board the high school is 37% complete with $14.53 million authorized and $24.71 million remaining; Fulton Elementary is 81% complete with $10.38 million authorized and $2.49 million remaining.

Claycomb Associates and Teal Construction representatives updated the Rockport‑Fulton Independent School District Board on progress under Bond 2022. Jamin Welch of Claycomb Associates and Josh Hansen of Teal Construction said the new high school is about 37% complete, with $14.53 million authorized to date and $24.71 million remaining against the project budget. They reported the Fulton Elementary project is about 81% complete, with $10.38 million authorized and $2.49 million remaining.

Trustees asked for clarification on schedule and budget contingencies; the Claycomb and Teal representatives fielded several questions but the board did not take any immediate action. The update closed with staff recommending continued monitoring and routine monthly reports to the board as the projects progress.