Comal County approves $59,723 change order for Public Health Emergency Operations Center
Summary
The court approved Change Order 41 for the Public Health Emergency Operations Center project totaling $59,723, funded by American Rescue Plan Act interest-earned funds; staff said there were no added contract days and substantial completion was previously met.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Comal County staff told the Commissioners Court that Change Order 41 for the Public Health Emergency Operations Center increases the project by $59,723 and recommends approval. "This change order...in the total amount of $59,723," a staff presenter said, explaining the changes included owner-requested adjustments, additional power to AV racks, TV mounts, light pole modifications and added entrance lighting.
Staff said the work represents a group of final items and that no additional days were added to the project's completion date; they reported substantial completion had occurred by Sept. 29. Commissioners moved and seconded the change order and the court approved it; funding will come from American Rescue Plan Act interest-earned funds.