Bond 2022 update: RFHS 42% complete; Fulton Elementary 86% complete, consultants report

Rockport-Fulton Independent School District Board of Trustees · February 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Claycomb Associates reported the High School project is 42% complete with $16.55 million authorized and $22.69 million remaining; Fulton Elementary is 86% complete with $11.06 million authorized and $1.81 million remaining.

Jamin Welch of Claycomb Associates delivered the monthly Bond 2022 construction status report to the board. He said the Rockport-Fulton High School project was 42% complete with $16.55 million authorized and $22.69 million remaining, while the Fulton Elementary project was 86% complete with $11.06 million authorized and $1.81 million remaining.

The update was presented as part of the facilities report; trustees heard the status and had committee updates from board members. The minutes do not record follow-up action or contingency decisions tied to the construction update.