Bond 2022 update: RFHS 42% complete; Fulton Elementary 86% complete, consultants report
Summary
Claycomb Associates reported the High School project is 42% complete with $16.55 million authorized and $22.69 million remaining; Fulton Elementary is 86% complete with $11.06 million authorized and $1.81 million remaining.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Jamin Welch of Claycomb Associates delivered the monthly Bond 2022 construction status report to the board. He said the Rockport-Fulton High School project was 42% complete with $16.55 million authorized and $22.69 million remaining, while the Fulton Elementary project was 86% complete with $11.06 million authorized and $1.81 million remaining.
The update was presented as part of the facilities report; trustees heard the status and had committee updates from board members. The minutes do not record follow-up action or contingency decisions tied to the construction update.