Maybrook schedules micro‑milling and paving for multiple streets in September
Summary
DPW Superintendent Thorp and Mayor Leahy outlined a three‑phase roadwork plan: micro‑milling (Sept. 9–12), fiber‑matting (Sept. 15–19), and paving (Sept. 22–26); affected streets and parking restrictions were published and municipal lots are available.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
DPW Superintendent Thorp and Mayor Leahy briefed the board on an upcoming road program that begins with micro‑milling Sept. 9–12, followed by fiber‑matting Sept. 15–19 and paving Sept. 22–26. Streets scheduled for paving include Blake Road, Crystal Drive, Palmer Court, Saracino Drive (from Country Club Drive to Blake Road), Greening Place and Watts Lane.
Residents on affected streets were notified and parking will be prohibited on the listed streets from 6 a.m. to 5 p.m. while work progresses. The village announced municipal parking lots at David Weiss Park and on Rakov Road will be available for displaced on‑street parking during construction. Greening Place curbing has been completed and the street is ready for the scheduled paving.
The board did not take a vote on the schedule; the items were reported as part of the Mayor's and DPW reports so residents should consult the village website for updates and potential changes due to weather.