Lena board approves major pay applications for Camp Street, Main/Townline and Lena Drive Inn

Village of Lena Board · August 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Village of Lena approved pay applications and change orders on Aug. 11, 2025, including a $198,736.92 payment for Camp Street improvements and a $163,334.67 payout for Lena Drive Inn drainage work; related change‑order language in the minutes was inconsistent on a contractor name.

The Village of Lena Board on Aug. 11 approved multiple contractor pay applications and associated change orders tied to ongoing street and drainage projects.

On a motion by Board member Christin Keeffer, seconded by Brandon Smith, the board approved Pay Application #1 to Martin & Company for Camp Street improvements in the amount of $198,736.92. The motion carried unanimously (all aye). The board also approved Pay Application #1 for Fischers for Main Street and Townline Road improvements and Change Order #1 for Fischer's Excavating.

The board approved Pay Application #2 for Lena Drive Inn drainage improvements in the amount of $163,334.67 on a motion by Dean Rood, second by Keeffer (all aye). Minutes also record approval of grouped change orders/pay applications described as 'pay application #1-5' in the record with an aggregate amount of $2,766; the meeting minutes show inconsistent contractor names adjacent to that line. The minutes flagged this line in the transcript — the board approved the amount as recorded, but the contractor reference in the minutes is unclear.

Village Engineer Brian Nott reported progress on related projects: Fischers completed the Milfred Street water main and storm sewer work is underway; Camp Street is awaiting site restoration; Townline/Main site restoration is ongoing. Nott said the Milfred Street project is a 55 working‑day contract and that he will count rain days for schedule adjustments.

Next steps: contractors will continue site restoration and the village will process the approved payments. The minutes show all motions on these items passed unanimously.