Engineer reports Dayton, Milfred and Camp Street work; Lena Drive Inn piping upsized to 36 inches
Summary
Village Engineer Brian Nott updated the board on multiple street and utility projects: Dayton Street costs are being finalized with Fischer, Milfred Street water-main work faced a Nicor delay, Camp Street paving and driveway work is scheduled, and piping under Lena Drive Inn was enlarged from 12 to 36 inches.
Get email alerts on the Transportation Public Improvements topic
No spam. Unsubscribe anytime.
Village Engineer Brian Nott summarized active infrastructure work around Lena, telling the board Fischer is finalizing numbers for Dayton Street and that Milfred Street work began but was slowed by a Nicor gas-main issue that has since been resolved. Nott described Camp Street as scheduled for paving and driveway completion in the coming week and said an additional inlet was added to address sump pump drainage.
On utility relocations at the Lena Drive Inn, Nott said crews “went to 36" pipes from 12" under the Drive Inn parking lot,” and said Frontier has completed relocations while Nicor was expected to finish work the following day before Kelsey Excavating begins. Nott also reported Fischer submitted a right-of-entry permit to allow work in the railroad right-of-way at Townline & Main.