Council approves hydrant risers for 2nd Street project change order
Summary
The Wessington Springs City Council approved a change order for the 2nd Street Project to add two risers for two fire hydrants at $1,285 each, following a presentation by Brosz Engineering.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Wessington Springs City Council approved a change order for the 2nd Street Project on April 8, 2026, to add two risers for two fire hydrants at a cost of $1,285.00 per riser. Eric Prunty, representing Brosz Engineering, met with the council to discuss the needed risers and project details.
Pat Fastnacht moved to approve the change order; Cherie Maxwell seconded the motion. The motion carried with four ayes and no nays. The council recorded the change order amount and authorized staff to proceed with the work on the project.