Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Boardwalk Project topic
No spam. Unsubscribe anytime.
Board hears boardwalk engineering complete but unstable ground may raise costs up to about $1 million
Summary
Staff reported the first phase of boardwalk engineering is complete but unstable ground may require another phase and additional work; alternatives are being discussed with EGLE and final approval will rest with county commissioners.
Get email alerts on the Boardwalk Project topic
No spam. Unsubscribe anytime.
The board was told the first phase of engineering on the boardwalk is complete, but unstable ground at the site may require an additional engineering phase and substantially raise costs. "!st phase of engineering completed, however another may be necessary at additional cost. Unstable ground being the reason. Alternatives being discussed with EGLE with a possible million dollar price tag," the minutes state.
Minutes indicate the project’s next step — whether to proceed with further engineering or pursue alternatives — rests with the county commissioners, who must give final approval to move forward. No procurement or contract award actions were recorded at the meeting.
