Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Broadband topic
No spam. Unsubscribe anytime.
Spring Creek broadband project about halfway complete; CC Communications files revised baseline with NTIA
Summary
CC Communications reported Spring Creek broadband is about 45% complete and will submit an NTIA extension request to match an updated baseline through 2027; environmental reviews and winter weather caused earlier delays, and some tracks remain to be finished.
Get email alerts on the Broadband topic
No spam. Unsubscribe anytime.
CC Communications told the Elko County commission that its Spring Creek broadband deployment under the NTIA Broadband Infrastructure Program is roughly 45% complete and that the company will file an extension request to match a revised baseline through 2027.
Mark Best of CC Communications said Tract 400 is substantially complete, Tract 300 is "all but splicing," and Track 100 (the golf course track) had not started at the time of the update. He explained early work was delayed by environmental reviews tied to federal funding requirements and by a severe winter that halted construction. "We're approximately 45% complete," Best said, and added that the company filed an updated baseline report with NTIA that was accepted and that the formal extension request will mirror that revised schedule.
Best also described practical matters: some locations already have fiber and must still meet NTIA baseline requirements (including run‑speed tests for customers on the network), and construction sequencing will be adjusted for field conditions. He thanked county staff for assistance in administering the grant and said audits to date produced no findings.
Why it matters: The NTIA grant funds rural broadband that affects internet availability and economic opportunities; the extension and revised baseline will set expectations for completion dates and federal compliance requirements.
What’s next: The company expects to proceed into remaining tracks (Pleasant Valley and then Track 200/100) according to revised schedules and will file the extension paperwork with NTIA.
