Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Drainage Project topic
No spam. Unsubscribe anytime.
City staff outlines multiple change orders on Raves Bayou drainage project; recommends resolution approval
Summary
City staff reported multiple change orders on the Raves Bayou drainage and detention-pond project and told council the work is largely reimbursed by CDBG-MIT grant funds; staff recommended approving attached change orders and a resolution to update the contract total.
Get email alerts on the Drainage Project topic
No spam. Unsubscribe anytime.
City staff presented a series of change orders for the Raves Bayou improvement and detention-pond work and recommended the council approve a resolution attaching change orders 3, 4 and 5. Rigo, the project representative, told the council the project previously approved at the June meeting had accumulated several supplemental line items including pavement removal, additional concrete, air-release valves and manholes, and concrete pumping. Staff said the work is included in the Fiscal Year 2024 capital improvement plan and that roughly 90% of the project is funded through CDBG-MIT grant funds; the city’s local share remains in effect for the balance.
Rigo explained the timing pressure on the contractor, noting a November deadline tied to reimbursement. Councilmembers asked for visual context and maps; Rigo said crews had already demucked portions of the channel and opened some lanes to allow sidewalk and other finish work. No separate contested vote on the change orders was recorded in the transcript; the consent agenda that included this item was approved by council earlier in the meeting. Council asked staff to continue updates and to work with adjacent property owners as the contractor completes work ahead of the grant deadline.
