Selectboard approves Amendment 1 for Winchester wastewater improvements; Sepe abstains
Summary
The Selectboard voted to approve Amendment 1—driven by NHDES requirements and adding a second resident engineer—for the town's wastewater projects, while expressing frustration about extra costs; the board was also briefed on the 5 Corners water-main work, booster station timeline and an EPA walkthrough scheduled for Aug. 4, 2026.
Get email alerts on the Wastewater Projects topic
No spam. Unsubscribe anytime.
The Winchester Selectboard on July 22 approved Amendment 1 to the town's wastewater contracts, authorizing an added resident engineer and related scope changes required by the New Hampshire Department of Environmental Services. The motion to approve Amendment 1 was made by Selectman Herbert Stephens and seconded by Selectman Jack Marsh; the board recorded a 4-0-1 vote with Selectman Theresa Sepe abstaining and asking that a letter be sent to the senator expressing displeasure about the additional expense.
The amendment was explained at a presentation by Colin O'Brien of Brown & Caldwell, who reviewed a project brief titled "Winchester Wastewater Project: Delivering Critical Infrastructure Improvements through Partnership." O'Brien told the board the additional resident engineer was a requirement from NHDES and said the consultancy now sees why that role is warranted after six months of work. "The worst-case scenario is not on the horizon at this time," O'Brien told the board when asked about risks.
Water/Sewer Superintendent Rick Meleski added the amendment will help the town complete necessary upgrades to the facility and get the work done "right," and praised Brown & Caldwell for supporting the town through contractor oversight. Board members pressed for regular updates; Marsh requested bi-weekly written summaries to be left at the Selectboard office, and O'Brien agreed to provide schedule and timeline updates.
Why this matters: the amendment raises the project's near-term cost and schedule oversight but was presented as necessary to meet funding-partner (NHDES) requirements and to ensure in-field engineering support during complex construction activities. The board recorded the approval formally in the meeting minutes.