Board reviews four options for aging West Elementary — renovate, add, rebuild on-site or build elsewhere

Spearfish School District 40-2 Board of Education · August 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architects from 3 Peaks and JLG presented four high-level options for West Elementary — renovate in place, phased addition plus renovation, full replacement on site, or build on a new site — with preliminary cost estimates ranging from the low tens of millions for renovation to roughly $39–50 million for new construction; board directed further fiscal analysis and teacher/community engagement.

Architects from 3 Peaks (Jason Robidoux) and JLG (Ron Olson) presented four high-level options for the district’s West Elementary footprint during an Aug. 4 work session: 1) continue deferred maintenance; 2) phased addition (add gym and kindergarten) with staged renovation; 3) replace the building on the existing eight-acre site in two phases; or 4) acquire a different site and build new.

"The 4 options that are starting to come to the surface…there’s certainly a lot of variables to these," Jason Robidoux said, cautioning the board that the designs and numbers were conceptual and intended to narrow the funnel of possibilities. 3 Peaks and JLG walked the board through tradeoffs for each alternative, calling attention to asbestos tile, an old pneumatic HVAC control system, limited site acreage and storm-drain easements that constrain on-site replacement options.

Ron Olson, speaking to the retrofit vs. new-build trade-offs, emphasized site constraints and code changes that drive complexity: "Some of those beams... they're past or they're beyond what he would consider, margin of error that you could just leave alone as a grandfather sort of approach," he said, arguing that snow-mitigation and structural work are real risks for a renovation-only path.

Architects and staff presented early cost ranges rather than firm estimates: renovation-only scenarios were discussed near $18 million, phased new-plus-renovation approaches and replacement scenarios were discussed in the high tens of millions, and architects noted that a new site build could vary widely depending on land and utility costs (the team used +/- $50 million as an illustrative uncertainty range for some off-site scenarios). Presenters and staff repeatedly stressed these were conceptual planning numbers and that more detailed design and delivery planning is needed.

Board members asked about capacity implications (renovation-only preserves a ~400-student footprint; phased or new options could expand to ~600 students and move Mountain View grades), the timeline for community engagement (teacher sessions in late September; community sessions Oct.–Dec.), and how to balance the capital program with deferred-maintenance needs across the district. The architects said a phased approach could allow the district to keep students on site but would take multiple years, while a replacement or off-site build changes drop-off, access and parking considerations.