Road and Bridge updates: bridge work continues on County Road 274; routine maintenance underway

Coryell County Commissioners Court · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Road and Bridge staff reported structures and earthwork are in place at the County Road 274 bridge project, mowing and brush cutting continue, and procurement delays have affected materials availability for planned operations.

Mr. Lakeland delivered the monthly Road and Bridge report: crews are working on the County Road 274 bridge where structures and earthwork are in place; bridge-builder communication continues and some materials are backordered for months. He said routine mowing, brush cutting and rock work are ongoing countywide.

Commissioners asked about coordination with nearby city annexations and plat approvals; staff said they are compiling length and width data for state database submission and would share bridge acceptance documentation with county staff. There were no actions taken beyond the report.