Water operator reports plant upgrade progress and new remote control panel
Summary
The water department reported that seasonal facilities were winterized, a new touchscreen control panel was installed enabling remote monitoring, and a malfunctioning well starter has been ordered for replacement; State Health Department review of plant upgrade plans is underway.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Clerk Holder read the water‑project report from operator Phil Landrieu: the department completed sampling and reporting, shut down and winterized summer water systems (Watawau Park, Bark Park, Green Lake Park Beach), and installed a new control‑panel touchscreen to allow remote access to plant operations.
Landrieu also reported a malfunctioning well starter; a replacement starter has been ordered and will be installed on arrival. He said the State Health Department is reviewing revised plant upgrade design plans; once approved, the village will begin the plant-upgrade work. The water operator thanked building/grounds and DPW staff for assistance with repairs and excavations.