Public Works: chip‑sealing behind schedule; county expects about 35 miles this season

Jefferson County Board of Commissioners · July 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported slower than usual chip‑seal progress after equipment and staffing issues; the department said it expects to complete about 35 miles this season (down from typical 50–60 miles) and aims to increase tanker runs if staffing allows.

Mike Carter, Public Works director, told commissioners the county's chip‑seal program is a bit behind schedule because of a new chipper learning curve and staffing cuts; the department now expects to finish about 35 miles this season compared with the normal 50–60.

"We ended up about 35 with the cuts," Carter said, adding that on two tankers they average about 2.25–2.5 miles per day and could get closer to three miles on long straightaways. He said the department will prioritize road oil and may postpone painting or striping on some roads because of budget reductions.

Commissioners asked about timing for painting and the courthouse parking lot; Carter said striping is usually done in the fall and that the courthouse questions should be routed to the county clerk for specifics.