Council approves $16.8M GMP amendment for lift station; project total now about $19.78M

Castle Rock Town Council · December 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a second contract-price amendment for the Plum Creek lift-station and force-main project. Staff said the contractor GMP for construction is $16,766,000, the design-build contractor package is about $18.4M and the total project cost is estimated at $19,780,000, leaving an additional $984,296 needed; ARPA funds will pay first.

Town staff updated council on the Plum Creek lift-station and force-main project and asked council to approve a second contract amendment so construction can proceed. Staff said the project is at roughly 90% design and that phase 1 will be built to 1,200,000 gallons per day, with a phase 2 expansion to 2,200,000 gpd handled later. Mark Henderson told council the initial GMP at 60% design was about $18.78 million; after negotiations contractor scope and costs were trimmed and the negotiated contractor construction GMP is $16,766,000, putting contractor-plus-design at roughly $18.4 million. Accounting for easements, land acquisition and other items, staff estimated the total project cost at $19,780,000 and said an additional $984,296 is needed to proceed.

Staff and council discussed timing and the risk of rebidding; Henderson said ARPA funding ($14 million) must be spent next year and that delaying to rebid could imperil that funding. Council voted unanimously to approve the amendment and move forward with construction procurement under the negotiated GMP.