Board awards wastewater pump replacement contract, approves UV-panel repair quote
Summary
The Board accepted the low bid from Municipal Pump Company for wastewater headworks pump improvements ($210,110) and approved a separate $10,971.62 quote from Viola Water Technologies for UV control-panel repairs and staff training.
Get email alerts on the Water Treatment topic
No spam. Unsubscribe anytime.
Staff recommended awarding the wastewater treatment plant headworks pump replacement project to Municipal Pump Company of Earth City, Missouri, as the lowest responsive bidder. Staff said three bids were received and the main differences were pump brand and markup; the recommended bid totaled $210,110. The board moved and approved the award.
Separately, staff presented a quote from Viola Water Technologies to repair the ultraviolet control panel at the wastewater plant and provide on-site staff training. The quoted total cost was $10,971.62 to be paid from the sewer and water repairs and supplies budget (the budget line was reported as approximately $60,000). The board approved that purchase as presented.