LJA's Don Cleary briefs commissioners on SPLOST projects and timeline

Dallas County Board of Commissioners · August 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Don Cleary of LJA presented the quarterly 0.25 SPLOST transportation update through June, reporting completed projects, underway work (Longview over 50% complete), upcoming right-of-way acquisition for Lumpkin Campground/State Route 53 projects, and a busy 2027 spending year.

Don Cleary of LJA presented the board with the second 0.25 SPLOST update, calling the report a snapshot of the county's IGA summary, collections, budgets and project commitments through June. He told commissioners the program is moving toward a busy 2027 for spending and construction activity.

Cleary walked commissioners through active projects, saying the Longview drainage and pavement repairs are over 50% complete and should finish later this summer after crews removed buried debris. He described the Lumpkin Campground corridor projects as advancing into right-of-way phases with one parcel remaining and sign/utility impacts still being resolved.

Cleary said the team has kicked off design on State Route 9 North at Perimeter Road, agreed with Georgia DOT on a roundabout concept, and expects surveys to begin soon. He noted Cowart Road has been awarded as a full-depth reclamation project and is moving to construction, and Couch Road has progressed through preliminary design as staff balance improvements and budget constraints.

The presentation included completed-project photos (Nightfire, Dogwood, Hanging Dog) and a highlight on Elliot Road, which was rebuilt via full-depth reclamation and came in on budget to provide an estimated 25-year road base. Commissioners asked sequencing questions about concurrent projects (Lumpkin, Whitmire, Red Ryder); Cleary emphasized prioritizing the roundabout and completing surveys and right-of-way work before overlapping construction phases.

No formal board action was taken during the informational presentation.