Avon details middle‑school atrium demolition, field and gym upgrades; project ~30% complete

Avon Central School Board of Education · January 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District leaders reported plans for demolition to create a middle‑school atrium, abatement over February break, approved field and gym work, and considered stage rigging/lighting as possible alternates. The capital project budget totals $24,247,000 with about 30% complete and $964,159 remaining contingency.

Superintendent Ryan Pacatte updated the board on facilities work tied to the 2022 referendum. He said demolition of a district hallway to create a middle‑school atrium will begin when office staff can relocate and that the district hopes to schedule abatement work over February break. Field and gym upgrades were discussed: field work is approved and ideally will be completed before summer; gym work awaits final design prior to bidding.

The minutes list the overall project funding: $23,890,000 from the 2022 referendum plus $357,000 from a prior referendum for a total of $24,247,000. The project is reported about ~30% complete; the contingency budget is $1,215,715 with $251,556 in change orders noted (about 20.6% used) and $964,159 remaining. Dr. Pacatte said certain alternates—such as stage rigging and lighting—could be added as alternates, special transfers or by referendum if needed.