Board approves $25,000 geotech testing after state flags soil on middle‑school gym site

Middletown Unified School District Board of Trustees · March 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved additional geotechnical services — $25,000 for deeper borings to 66 feet — after the California Geological Survey identified liquefaction risk in one of three borings. The testing must be completed and accepted by CGS before DSA approval and construction can proceed.

The board approved a $25,000 contract amendment to fund specialized drilling and lab work after the California Geological Survey (CGS) flagged a section of soil as potentially subject to liquefaction on the planned middle‑school gym site.

Project lead Ray Green told trustees that the original report encountered hard rock at 32 feet in the borings but one hole showed soil subject to liquefaction between 5 and 6.5 feet. He said CGS “has prescribed that we drill 66 feet” with a specialized rig and that the contractor expects to produce a final report within three to five days after borings are completed.

Ray described the options if testing confirms a wider problem: mitigation could require redesigning foundations or moving the building footprint, both of which would add cost. Ray and staff emphasized they chose a geotechnical firm with local experience; the board approved the additional service and staff said drilling is scheduled for the 19th, with CGS and DSA review timelines still controlling the overall schedule.

Board action: motion to approve additional services for Crawford Associates, Inc., passed unanimously.