Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Construction Update topic

No spam. Unsubscribe anytime.

YMCA pool shell complete; fill and leak test planned for mid‑December

Village of Shorewood Village Board · October 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Building department reported pool footings and floor are complete at the YMCA site; shell work is underway, a major concrete pour is planned, and the contractor expects to fill and test the pool for leaks around Dec. 18, contingent on exterior backfill and weather.

The village building department updated the board Oct. 28 on construction progress at the YMCA and its pool project.

The building representative said pool footings and the floor are complete and that crews are finishing the pool shell, with a large concrete pour scheduled and follow‑up pours the following week. “Their fill date at this time looks to be, middle of December, so they're hoping to be doing their water test for leakage right around the 18th,” the building department official said. Staff noted weather and exterior backfilling will determine final timing and that they are coordinating meter and water‑use logistics with public works and finance.

The building official said contractors have taken the hydrant meter for construction use, the permanent main meter is installed, and some details remain to be resolved about which meter will be used to fill the pool. No board action was required; staff will continue coordination with the YMCA and the general contractor.