Board approves $605,526 change order to convert water vaults to above‑ground PRV buildings

Village of Shorewood Board of Trustees · September 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board authorized change order #1 to Pratano Construction for $605,526 — converting two below‑ground vaults to above‑ground pressure‑reducing valve buildings on the 16‑inch transmission main — and waived formal bidding, citing safety, maintenance and IEPA/SRF approvals.

Public works staff asked the board to approve change order #1 to the Pratano Construction contract for the 16‑inch water transmission main, increasing the construction contract by $605,526 and raising the total to about $5.10 million. Staff said IEPA approvals were received and the revised design can be included in SRF funding.

“We are recommending to the village board that we approve change order number one and waive the formal bid process in the amount of $605,526 for our 16‑inch water transmission main project, increasing our construction contract to $5,103,143,” staff said. The presentation emphasized safety and operability: converting below‑ground vaults to above‑ground buildings avoids confined‑space daily entries, reduces reliance on sump pumps and dehumidifiers, and extends equipment lifespan.

Staff and an invited assistant public works director/consultant walked the board through examples of vault corrosion and the operational burdens of below‑ground equipment. After questions about cost and lifetime benefits, the board voted to waive the public bid requirement and approved the change order by roll call.