Council approves $119,119.94 repair contract to restore Royal Street underpass pump capacity

City of Beaumont City Council · August 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $119,119.94 contract to fabricate three spare impellers and refurbish pump #4 at the Royal Street Underpass Pump Station to keep stormwater pumping reliable until permanent replacements are available.

The City Council approved a $119,119.94 fabrication and refurbishment contract to restore capacity at the Royal Street Underpass Pump Station, which pumps stormwater for the MLK Parkway corridor between Franklin and College Streets.

Staff told council the submersible pumps have been failing because of age and abrasive stormwater conditions and that custom machining and fabrication were required because original parts are no longer available. The scope covers three spare impellers and refurbishment of pump #4; funding is available from certificates of obligation.