Council approves engineering agreement for 8th Street culvert and detention-basin analysis ($21,580)
Summary
Council approved a $21,580 engineering agreement to perform hydraulic analysis and design work for a culvert and detention basin on 8th Street to support future development and stormwater control.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
The council approved a professional-services agreement for hydraulic analysis and design work related to a culvert and detention basin on 8th Street.
An engineer (recorded in the transcript as the meeting’s agency official) described surveying, topographic work, hydraulic modeling and proposed excavation and storage approaches intended to manage peak stormwater flows. The agreement presented to the council covered modeling, profile development and design deliverables and listed a total fee of $21,580.
Chair (S2) moved to approve the agreement and a council member (S1) seconded the motion; the transcript records affirmative votes following the motion. The council’s action funds design-phase work intended to enable development to move forward in the area by addressing drainage and detention capacity.
Speakers who discussed the item included the agency official/engineer (S2) and council members (S1). The motion appears in the transcript and was recorded as carried; the motion text in the record requests approval of the stated agreement and fee.
Speakers quoted: "The client... we're providing both services at a total of $21,580," (Agency official, S2).