Contractor updates gym projects; Tallmadge near completion, middle-school start pending geotech checks

Middletown Unified Board of Education · February 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Van Pelt representative Ray Green told the board Tallmadge Gym is finishing with a $100,000 parapet cap ordered and the middle-school gym is ~85% through DSA review; unknown soil conditions may require additional drilling before an April start.

Ray Green, speaking as the Van Pelt representative, reported construction progress on two capital projects. He said the Tallmadge Gym is finishing work and that a parapet cap material order of roughly $100,000 has been fabricated and is being installed, which will close out that project. “The vendor was cautious about ordering parapet cap because it's about a $100,000 of the material,” he said.

Green said the middle-school gym project is about 85% through Division of the State Architect (DSA) review and, if soil testing and approvals proceed as expected, an April start is possible. He noted suspect soil between about 4 feet 8 inches and 6 feet 7 inches deep that may require additional borings and testing before construction can proceed. The board asked clarifying questions about timelines and cost exposures; Green said he would return with final financials and a notice of completion when Tallmadge is closed out.