Hutto ISD outlines progress on Hutto High modernization and plans aggressive timeline for High School No. 2
Summary
District staff reported construction progress at Hutto High and Lee Martinez Elementary, described negotiating contractor costs, and said civil engineering and bid packaging aim to place earthwork contracts in March–April to meet an ambitious schedule for High School No. 2.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Operations staff said the dance area at Hutto High is nearly complete and crews are drilling piers and pouring concrete for a new gym (phase 4). Staff described on-site work including temporary accommodations for athletics and said CORE reports weekly schedule progress.
District leaders also reviewed planning for High School No. 2: Dunaway Engineering will provide civil engineering, and staff warned the effort requires multiple agency permits and coordination (water easements, traffic signal integration and a potential pedestrian beacon). Officials said they expect to issue two early bid packages (1A/1B) so subgrade and civil work can begin in March–April, subject to procurement and coordination with external agencies.