Board approves nearly $5 million total for DAEP renovations
Summary
Barbers Hill ISD trustees accepted a construction manager at-risk Guaranteed Maximum Price for DAEP renovations: GMP $4,286,884 plus $713,000 in soft costs for a total of $4,999,884; motion passed 7-0 on Sept. 22.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Barbers Hill ISD Board approved acceptance of the Guaranteed Maximum Price (GMP) for the DAEP Renovations Project on Sept. 22. Executive Director of Planning & Facilities Patrick Hendricks presented subcontractor pricing and the recommended GMP. The materials show a GMP of $4,286,884, CM general conditions and fees included, and soft costs of $713,000 for a total project cost of $4,999,884; Trustee Becky Tice moved to accept the proposed total GMP and soft costs and the motion passed 7-0.
Hendricks' presentation noted subcontractor pricing was received Sept. 4 and Purcell Construction completed the evaluation of pricing and scope. The board's action authorizes the district to proceed on the DAEP renovations under a Construction Manager at Risk delivery method using the presented GMP pricing.