Board approves $2.37 million GMP and soft costs for BHISD central plant equipment
Summary
Trustees approved a Guaranteed Maximum Price plus soft costs totaling $2,366,746 for pre-purchasing central plant mechanical and electrical equipment to meet long lead times for new facilities.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
The Barbers Hill ISD Board voted unanimously Oct. 27 to accept a Guaranteed Maximum Price (GMP) and soft costs totaling $2,366,746 for the Central Plant Equipment Pre-Purchase Package, intended to secure long-lead mechanical and electrical equipment for the new Higher Education Facility and Primary School North.
Executive Director of Planning and Facilities Patrick Hendricks explained the pre-purchase was necessary because of long equipment lead times. The board packet breaks down the GMP as a $2,099,357 equipment subtotal, $89,643 in general conditions, $43,780 in CM at Risk fee, and $133,966 in total soft costs. Trustee Fred Skinner moved to "accept the proposed total GMP and soft costs price of $2,366,746.00 for the BHISD Central Plant Equipment Pre-Purchase Package using Construction Manager at Risk project delivery;" Trustee Clint Pipes seconded the motion and it passed 7-0.