Trustees approve $2.2 million guaranteed maximum price for transportation parking expansion
Summary
The Barbers Hill ISD board accepted a $2,032,836 guaranteed maximum price and $2,203,604 total cost for a transportation parking lot expansion to add 30 bus spaces and 13 white-fleet spaces; the motion passed unanimously.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Patrick Hendricks, executive director of planning and facilities, told trustees the construction manager at risk received subcontractor pricing and recommended acceptance of the guaranteed maximum price for the Transportation Parking Lot Expansion. "BHISD Transportation Parking Lot Expansion: $ 1,857,998.00 CM at Risk General Conditions at 6.41%: $ 119,098.00 CM at Risk Fee at 3% $ 55,740.00 Guaranteed Maximum Price: $ 2,032,836.00 TOTAL COSTS, GMP + SOFT COSTS $ 2,203,604.00," the packet states.
The board moved to accept the proposed total GMP and soft costs using a Construction Manager at Risk delivery method. George Barrera, trustee, made the motion and Becky Tice seconded; the vote was 7–0 in favor. The project scope in the packet describes 30 new bus parking spaces and 13 white-fleet parking spaces; trustees did not amend the GMP at the meeting and directed staff to proceed with contract execution and next steps for procurement and scheduling.