Bond construction work progressing; ADA ramps to be redone and $46,000 repayment projected
Summary
Mazanec Construction is finishing outside canopies and closeout documents for Bosqueville ISD; five ADA ramps and the main ramp must be redone, work is expected complete by January, and the district was told an estimated $46,000 will be repaid to the district.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
At the Nov. 10 Bosqueville ISD meeting, the board received a construction update related to bond-funded work. The minutes state Mazanec Construction is completing outside canopies at delivery areas and the front of Buildings 1 and 2 and continuing work on closeout documents.
The update said five ADA ramps and the main ramp will need to be redone, with all work expected to be completed by January. The minutes record an "estimated repayment of $46,000 back to the district." No formal action on the construction items was recorded during the meeting.