High-school bond construction about 30% complete; storm shelter and parking among near-term tasks

Castleberry Independent School District Board of Education · August 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Bond program manager reported the 2024 high-school bond program is roughly 30% through construction, with roof decking and storm shelter work underway; the team anticipates partial access to areas A and B next summer and noted a $500,000 saving on the waterline review.

Cameron Holloman, bond program manager, gave a construction update on the 2024 high-school bond program and said the project is roughly 30% complete and remains on schedule. "From a financial perspective, we're about, 30% through construction," he said, and walked the board through photos and drone footage showing decking, new roofing and interior progress.

Holloman highlighted three near-term priorities: completing underground sitework and student parking, addressing a city waterline connection (anticipated September start), and finishing storm-shelter components that account for a substantial portion of new-construction costs. He said coordination with consultants and the city produced a roughly $500,000 savings on the waterline. Board members and staff asked technical questions about parking logistics, phasing and safety measures; Holloman said additional bids and soft-cost work remain to be finalized.