Board accepts Austin Elementary parking-lot work and authorizes final payment
Summary
Board approved Change Order No. 2-A-001 and accepted completion of Austin Elementary Parking Lot Replacement Subproject No. 2-A; final contract sum reported as $621,379.39.
Get email alerts on the Construction Payments topic
No spam. Unsubscribe anytime.
Finance Manager Angel Grant reviewed the completed Austin Elementary Parking Lot Replacement Subproject No. 2-A and presented the contract figures: Guaranteed Maximum Price $722,635.00; Change Order 2-A-001 -$101,255.61; Final Contract Sum $621,379.39. Trustees were asked to accept the work as complete and authorize final payment.
Trustee Denise Intemann moved to approve Change Order No. 2-A-001, accept the work as complete, authorize final payment, and empower the superintendent to execute final completion paperwork; Trustee Cade Taylor seconded and the motion passed unanimously.