Palacios ISD Board Certifies Final Payment for GMP 3; Projects Complete $113,122 Under GMP
Summary
The Palacios ISD Board approved a final payment of $0.00 to Drymalla Construction Company, certifying total project costs of $43,059,112 for the New PreK–5 campus, fine arts and football renovations — $113,122 below the approved Guaranteed Maximum Price.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
The Palacios ISD Board of Trustees voted April 13 to approve the final payment certificate for the district's Guaranteed Maximum Price (GMP) 3 projects, certifying a total project cost of $43,059,112.
The motion to approve a final payment of $0.00 to Drymalla Construction Company — reflecting a total cost $113,122 below the approved GMP — was made by Trustee Fabian Marroquin and seconded by Trustee Carl Filip. Board President Becky Aguilera recorded the vote as Yea; Trustees Marroquin, Filip and Haley Garcia also voted Yea. Trustees Brian Busby, Dane Kubecka and Ron Laws were absent. The motion passed 4–0.
The approved scope listed in the meeting materials and on the agenda includes a new PreK–5 campus plus fine arts and football renovations. The transcript does not specify remaining closeout tasks or retainage amounts beyond the finalized payment certificate. The board did not attach an immediate implementation timeline in open session.
Board action on the certificate completes the district's internal approval step for project closeout; any contractor claims or outstanding administration items were not recorded in the open minutes.