Engineer reports Phase IV sewer nearing wrap‑up; Route 20 preconstruction scheduled

Town of Nutter Fort Town Council · October 22, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town engineer Ryan Holcomb reported Phase IV sewer line work is complete with two weeks of concrete and sidewalk work remaining before paving, Route 20 Corridor preconstruction is set for Nov. 14, and Phase II AMD's NEPA assessment was resubmitted for final approval.

Engineer Ryan Holcomb updated the council on multiple capital projects. He said Phase IV sewer line work is complete and the contractor has approximately two weeks of concrete and sidewalk work remaining before paving begins; a change order covering concrete steps, stored materials and quantity adjustments will be presented at the next meeting.

Holcomb reported Phase V sewer is on hold. For the Route 20 Corridor project he said the bid opening was Oct. 9, 2024, and a preconstruction conference is scheduled for Nov. 14, 2024 at Town Hall; he expects to present a recommendation of award at the next meeting. On mine‑related work, Phase I AMD closeout is underway with a forthcoming Change Order 3 for paving and screening; Phase II AMD’s NEPA environmental assessment has been resubmitted for final approval before submittal to the Office of Surface Mining.