Commissioners approve $7,200 change order and July 15 completion extension for JCD23FM repair
Summary
Faribault County approved Change Order #1 totaling $7,200 to bury clay and reshape 3,600 linear feet of berm on the JCD23FM repair and extended the completion date to July 15, 2026.
Get email alerts on the Drainage Projects topic
No spam. Unsubscribe anytime.
The Drainage Authority approved Change Order #1 for the JCD23FM repair totaling $7,200 to bury clay and reshape 3,600 linear feet of berm, and it approved an extension of the project's completion date to July 15, 2026. The minutes record the motion as "Loveall/Young motion carried unanimously to approve Change Order #1 for JCD23FM Repair totaling $7,200.00 for burying clay and reshaping 3,600 linear feet of berm and extend the completion date to July 15, 2026."
Commissioner Tom Loveall moved the measure and Commissioner Greg Young seconded. The change order and schedule extension were approved without recorded dissent; the meeting minutes do not show contractor objections or a revised cost schedule beyond the $7,200 amount.