Board authorizes oversight for controlled demolition and asbestos work at 15 Church Street
Summary
Trustees authorized a contract award and third‑party oversight for controlled demolition with asbestos abatement at 15 Church Street, moving a previously delayed project back into active work.
Get email alerts on the Demolition And Hazardous Materials topic
No spam. Unsubscribe anytime.
The Greenwood Lake board approved a resolution to authorize award of a request-for-proposal for controlled demolition with asbestos abatement at 15 Church Street and to appoint a third-party overseer for the project. The mayor noted the item had been delayed but is now moving forward.
Officials said the third-party overseer will supervise demolition and abatement work to ensure compliance with applicable procedures. Trustees approved the resolution by voice vote. The board did not provide contractor names in the meeting discussion; staff will finalize award paperwork and schedule demolition and required notifications.