Town updates: digester and slip‑lining projects advance; EPA grant coordination for water tank
Summary
Town sewer superintendent reported the digester project is in final DEC review and slip‑lining is about 75% complete; board authorized signing a professional services agreement to coordinate a $1,000,000 US EPA grant for a water storage tank replacement.
Get email alerts on the Water Sewer Projects topic
No spam. Unsubscribe anytime.
Town sewer superintendent Majori updated the board on major utilities work: the wastewater digester project is in final review by the New York State DEC and the town is finalizing equipment specifications in preparation for bidding; slip‑lining of sewer mains is about 75% complete. Majori said the project includes an asset management grant that adds cybersecurity work and that DEC will require formal asset management plans for sewer and water operators.
Separately, Supervisor Quigley moved to authorize the supervisor to sign a professional services agreement with Blauer Associates to assist with coordination and paperwork for a $1,000,000 US EPA capital grant the town received to replace a water storage tank. The board approved the motion. Majori emphasized that the town's sewer controls are locally operated (not remotely accessible) and that cybersecurity training and protections are part of present and upcoming compliance efforts.