Commissioners accept $201,940 in additions to Water Treatment Plant GMP from Bowen Engineering

Board of Fayette County Commissioners · June 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Fayette County approved an amended Guaranteed Maximum Price (GMP) from Bowen Engineering adding $201,940 in scope to the Water Treatment Plant project, including items such as additional heat trace ($47,868) and a fire alarm addition ($53,483).

The Board of Fayette County Commissioners on June 29 accepted an Amended Guaranteed Maximum Price Amendment from Bowen Engineering Corporation for the Water Treatment Plant project adding $201,940 in additional items.

The minutes list the amendment's line items and costs: Additional Heat Trace $47,868; CL‑17 Relocate $16,321; Fire Alarm Addition $53,483; Men's Locker Change $10,854; Mezzanine Barricade $16,524; Additional Ductbank Conduit per RFI‑98 (Electric) $15,489; Temp Power at Lagoon 3 (Phase 2 Scope) (Electric) $24,074; Elevated Tank Work (Electric) $9,132; Added Heat Shield to IRH‑3 $8,195. The resolution was moved by Mr. Fleak, seconded by Mr. Anderson, and approved on unanimous roll call.

The minutes do not elaborate on the procurement or funding source for these additions; they were described as "deemed necessary" by the county operations team and recommended for approval in the meeting record.