Consultant outlines arena renovation timeline and $6.325 million project estimate

Town Board of the Town of Alexandria · November 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A presenter named Andrew told the board the arena addition and renovation design is underway and preliminarily estimated at $6,325,000, with construction bids planned after final design and an anticipated substantial completion in November.

Andrew presented the board with a design and procurement timeline for the arena renovation and addition, describing design milestones, a planned bidding schedule and the project budget.

He said schematic design is complete, design development is underway, construction documents are expected by late January/early February, and the town will post a four-week bid period with an anticipated March award. On schedule, he said substantial completion is expected in November, with final completion and punch-list work wrapping up before year-end. Andrew described four separate prime contracts (general/site/asbestos abatement, plumbing, mechanical, electrical) and four bid alternates: scoreboard replacement, audio system, arena lighting, and a full arena HVAC system including dehumidification.

On costs he stated, “So the total project budget is $6,325,000,” and explained that figure includes a $5,000,000 construction subtotal, $750,000 in soft costs and a recommended 10% contingency ($575,000). He noted asbestos abatement will be required in the concession room and that the main parking lot will be closed during a portion of construction, affecting the school and village traffic patterns. Board members discussed staging, town in-kind demolition work, and recommended monthly project meetings including an owner-architect-contractor (OAC) process during construction.