Board discusses LaBerge engineering agreement, DOT right‑of‑way work and village cost share
Summary
Trustees discussed a proposed LaBerge consulting and engineering agreement originally described as $935,000; the firm reportedly offered a $100,000 reduction and the village would cover 20% of costs. Trustees explored DOT-required right‑of‑way mapping, appraisals and potential eminent domain processes and were warned cost‑plus contracting would delay the project.
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
The board debated particulars of a proposed engineering and consulting agreement with LaBerge for a DOT-related street project. "So as you remember, this was a $935,000 lump sum contract for consulting, engineering, and other stuff," the presiding officer said, adding the firm had agreed to reduce its price by $100,000. The chair told trustees the village would be responsible for 20% of costs under the grant structure.
The chair outlined what the contract would include: abstracts and maps from title and right‑of‑way searches, plans and cost estimates, attendance at public hearings, appraisals and negotiation for property acquisition. He warned that DOT allows specific contract types (lump sum, cost‑plus net, cost‑plus gross) and that converting to a cost‑plus model would require DOT approval and an audit of the firm, likely adding roughly nine months to schedule.
Trustees asked practical questions: how parcel owners (including out‑of‑state owners) would be contacted and what would happen if owners could not be reached. The chair said DOT could acquire necessary property through eminent domain if owners did not respond, though owners have opportunities to negotiate the details that are included in DOT plans. Trustees also asked about utility poles; the chair said the job was designed without moving poles and that limited encroachment into sidewalks may remain ADA‑compliant.
The board did not finalize the agreement at the meeting and said it would revisit the contract scope and terms at the next meeting on Wednesday. Officials said they are aiming for construction in the 2026 season but noted timing and final costs depend on DOT approvals and right‑of‑way work.