Committee approves two consultant invoices totaling about $132,000; oversight process explained

Nashua Board of Aldermen (Infrastructure Committee) & Library Board of Trustees (joint meeting) · August 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The joint committee approved two invoices — LeftField OPM for $64,349 and DesignLab for $68,100 — after questions about review and deliverables. Administration explained invoice review practices and a chair-level emergency approval threshold for change orders.

The joint committee voted to approve two invoices tied to schematic-design work. The first motion approved LeftField invoice #196342 for services through June 30, 2026 in the amount of $64,349. Committee members asked whether invoices undergo review for time and expense; Director Cummings said the owner's project manager and city staff conduct review before recommendation.

The committee also approved a DesignLab invoice for $68,100 representing 15% of schematic-design services plus a 3D scan and survey. Trustee Getty asked whether a schematic design existed to justify the 15% billing; presenters said schematic layouts were shown in the presentation and that the firm had completed roughly 28% of schematic work while invoicing 15%.

On process, Cummings explained payment and contract practices during construction: invoices and contracts are brought before this committee; the chair historically has limited authority to approve emergency change orders up to $50,000 and the director can approve up to $10,000 by ordinance; those approvals are reported back to the committee. Both invoices were approved by voice vote.