Council accepts wastewater plant equipment project; holds final payment for 30 days

Cresco City Council · August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Cresco City Council on Aug. 3 accepted final work on a $1.53 million wastewater-equipment replacement project, noting the construction contract was $1,585,000 with a final total of $1,529,000 and directing staff to hold final payment for 30 days pending punch-list completion.

The Cresco City Council voted Aug. 3 to accept the wastewater treatment plant age-related equipment replacement project and to hold the final contractor payment for 30 days while minor punch-list items are completed.

Scott, the staff presenter, said the work addressed several aging components — the screw pump, final clarifier, process piping and digester building — and added a nonpotable washdown system for the facility. "The construction side of this, the contract price was 1,585,000 and total is 1,529,000," he said, noting the project came in under the original estimate by roughly $45,000 because less steel was needed in the clarifier and the digester building was not painted.

Council members discussed the remaining punch-list items and the practice of holding final payment until those items are remedied. The motion to accept the project and hold the final payment for 30 days carried on a roll-call vote. The council also approved pay request No. 10 to Blaze Act Corporation for $13,775 related to the project.

Why it matters: accepting the project finalizes nearly all work on a multi-component capital improvement and triggers the 30-day retention period before the city issues the final contractor payment. Staff said the retention period provides time to verify and require corrective work on any outstanding items.