Drain reconstruction change order approved, adds $20,944 to Smith Northrup Wetzel project
Summary
The Allen County Drainage Board approved Change Order #1 for the Smith Northrup Wetzel Drain reconstruction, adding $20,944.37 for tree removal/utility coordination, a road crossing (to be covered by ACHD), and driveway rebar replacement.
Get email alerts on the Infrastructure Funding topic
No spam. Unsubscribe anytime.
ACSO presented Change Order #1 for the Smith Northrup Wetzel Drain reconstruction (Doc #26-119), which increases the project cost by $20,944.37. The three line items are an additional $8,250.00 for tree removal and utility coordination; $11,163.20 for the Wheelock Road crossing (ACHD indicated it will cover that item); and $1,531.17 for driveway rebar replacement.
Ronald W. Turpin moved to approve the change order and Richard E. Beck Jr. seconded; the motion carried. ACSO recommended approval. The minutes record that ACHD will cover the Wheelock Road crossing cost; the board did not record line-by-line votes in the public minutes.