Plain City staff outline Shepherd/Converse Avenue reconstruction: sidewalks, drainage and bid date
Summary
Staff updated council on the Shepherd/Converse Avenue reconstruction project: bid closes March 17, project will add new water lines, a 7‑foot sidewalk on the west side, gutters/catch basins to reduce standing water, and maintain two‑way traffic with parking on one side.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Village staff briefed the council on the Chevron/Converse Avenue reconstruction project and gave a timeline and scope for the upcoming work.
Staff said the bid for the reconstruction closes March 17 and that construction will replace water lines and pavement, install a 7‑foot sidewalk on the west side, add gutters and catch basins to address standing water, and preserve two‑way traffic and parking on one side where feasible. Staff will notify residents via mail, social media and the village newsletter and asked residents to keep driveways accessible during construction.
The presentation included photos of standing water from a recent storm that staff said accelerated pavement deterioration and justified the project. Staff noted an intent to preserve existing tree stands where possible and to tie the project into future quadrants to the south as part of a longer-term street improvement plan.
No vote was required; staff will proceed to bid-opening and bring the contract award to council for authorization when award recommendations are available.