Board approves $11,297.92 change order for county jail HVAC upgrade

Blackhawk County Board of Supervisors · August 4, 2026

Summary

Facilities director Rory Giving told the board change order #003 for the jail HVAC increases the contract by $11,297.92 to add digital controls for energy recovery ventilators and should represent the final payout for the project; the board approved the change order by roll call.

The board approved change order #003 to the Young Plumbing and Heating Company contract for Blackhawk County Jail HVAC and building automation upgrades, adding $11,297.92 for direct digital-control work tied to two energy-recovery-ventilator units.

Rory Giving, facilities director, explained a discrepancy in the original design required the additional controls work: "This puts the total project $11,297.92 over the original contract sum, and this should be the... final, we should be seeing the final payout for this project." He told the board that the systems originally had a standalone operating system and the current work integrates controls with the new operating system.

Supervisors asked no substantive follow-ups, and the resolution passed by roll call.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source