Piedmont Park ADA access and swings project underway; staff says work timed before school start
Summary
City staff reported construction is underway on the Piedmont Park ADA access and swings project with Modernscape Innovations; demolition and grading are complete in places, Daria (HortScience) has visited to review tree roots, and staff expects roughly a four-week timeline with coordination for school pedestrian safety.
Get email alerts on the Park Infrastructure topic
No spam. Unsubscribe anytime.
City staff told the Park Commission that the Piedmont Park ADA access and swings project is under construction with contractor Modernscape Innovations. Work completed to date includes grading and removal of concrete paving; staff said they have addressed some drainage questions and that HortScience staff (Daria) visited the site to review tree-root conflict areas.
Nancy (staff) said the project schedule was coordinated with Piedmont Unified School District to minimize conflicts at school start and estimated a roughly four-week construction window for the work described. Commissioners had no substantive objections and moved on to the next project update.