Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Public Works topic

No spam. Unsubscribe anytime.

Chadron approves $395,940.50 contract adjustment after storm damage on Stockade Road project

City of Chadron City Council · July 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order No. 2 for the Stockade Road Improvement Project, increasing the contract to $395,940.50 to fund shoulder stabilization, additional erosion control blanket and seeding after storm damage; NDOT will reimburse most costs except the City's share for street lighting.

The City Council on July 20 accepted Change Order No. 2 for the Stockade Road Improvement Project, approving an adjusted contract total of $395,940.50 for Paul Reed Construction & Supply to cover shoulder repairs, additional erosion-control blanket and seeding needed after storm damage.

City Manager Tom Menke told the council the work was necessary to stabilize the roadway shoulder and that the contractor will be responsible for watering newly seeded areas to encourage vegetation growth. Menke said the Nebraska Department of Transportation will reimburse the remaining costs associated with the change order except for the City's share related to street lighting improvements. The resolution (No. 2026-60) passed unanimously.