Chiloquin gym, Lost River and Crater Lake updates reported; Crater Lake cost about $3.2M
Summary
Superintendent Glen Szymoniak reported that the Chiloquin Jr/Sr High gym is scheduled for completion Aug. 11, 2025; Lost River Community Center is complete except for bleachers; and Crater Lake Learning Center is nearly complete with staff moving in and costs to date of approximately $3.2 million.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Superintendent Glen Szymoniak updated the budget committee on several capital projects. He said the Chiloquin Jr/Sr High School gymnasium is scheduled to be completed by August 11, 2025, Lost River Community Center is complete except for bleachers, and staff have begun moving into the Crater Lake Learning Center.
Szymoniak reported the cost to date for the Crater Lake Learning Center is approximately $3.2 million. Committee members did not take a vote on project budgets during the meeting; project timelines and remaining work items will be tracked by district staff.