Board approves outfall survey, clamp fabrication and effluent pump removal
Summary
The Board authorized up to $8,740 to remove an effluent pump and approved a set of ADI jobs totaling $48,450 for an outfall underwater survey, clamp fabrication, and future replacement at Joint 45.
Get email alerts on the Operations And Maintenance topic
No spam. Unsubscribe anytime.
The Board approved a series of operations and maintenance expenditures on March 23, including spending up to $8,740 with DXP to remove an effluent pump and approving three ADI job items for outfall work. ADI Job #02-26 was approved for up to $16,000 for an outfall underwater survey; ADI Job #03-26a for up to $9,500 to fabricate an outfall clamp; and ADI Job #03-26b for up to $23,000 in FY 26-27 to replace the clamp at Joint 45. The three ADI items were approved together for a combined $48,450.
The motions were made by Director Andrea Shepard and seconded by Director Jim Sullivan, with all votes recorded AYE: 3 (Shepard, Miksak, Sullivan). Superintendent Ryan Rhoades provided staff comment on the items. The minutes do not provide further technical details about survey scope or schedule beyond the approved spending limits.