Cambria board: groundbreaking expected early September; restroom may delay full opening
Summary
Staff told the board a public works agreement would be on next week's agenda (recorded as Aug. 13); the contractor's mobilization time is about three weeks with an expected early‑September groundbreaking and a 3–4 month construction window, while the restroom has an estimated 10‑month lead time and could delay full opening.
Get email alerts on the Construction Timeline topic
No spam. Unsubscribe anytime.
The board heard scheduling details for the Cambria State Park skate park: staff said a public works agreement will be on the next board agenda (recorded in the meeting as August 13). The general manager said the contractor's mobilization time is about three weeks after contract execution, which places a likely groundbreaking in early September, contingent on calendar events such as Pinerado.
Board members and staff estimated construction of the skate park features could take "3 months, maybe 4"; staff also referenced a 180‑day completion term mentioned in the record. Participants noted weather (an expected El Niño) could affect the schedule. The district explained that once features are complete, it will apply for a temporary occupancy permit to allow public use while the restroom is still pending.
Staff stated the restroom has an approximate 10‑month lead time, which will likely extend the timeline for full project completion. The meeting record shows staff planning to place the public works agreement on next week's agenda so the contract can be executed and mobilization can begin.